Company Overview
Flagship Project

Company Overview

Patuakhali 1320 MW Coal Fired Thermal Power Plant: Driving the nation's energy future with high-efficiency ultra-supercritical technology.

Project Overview

Generation Capacity
1320 MW

Dual units of 660 MW each. Unit 1 commissioned January 2025, Unit 2 April 2025.

Land Area
915.74 ACRES

500 leased + 30 for resettlement.

Established

21 December 2017

Coal Source

Indonesia

COD Target

April 2026

offline_bolt Operational Status

Unit 1

Jan 2025

Unit 2

Apr 2025

IOD

Sep 2025

COD Target

Apr 2026

Patuakhali 1320 (2×660) MW Coal Fired Thermal Power Plant is going to be another mega project of People's Republic of Bangladesh. It is another dream project for the people of Southern Part of Bangladesh. To implement this project and to fulfill the dream, two state-owned companies, Rural Power Company Limited (RPCL), Bangladesh and NORINCO International Cooperation Limited, China formed a Joint Venture Company named "RPCL-NORINCO Intl Power Limited (RNPL)" on December 21, 2017. The motto of this company is to bring electricity service all over the country including marginal areas.

Bangladeshi state-owned company RPCL selected the site at Kalapara Upazilla under Patuakhali District through detail feasibility Study and Environmental Impact Assessment in 2016. RPCL acquired 921.74 acres of land and 500 acres handed over to RNPL officially as long-term Land Lease Agreement in 2019. BPDB will purchase all the electricity generation from the power plant. Following this process Power Purchase Agreement (PPA) signed between BPDB and RNPL on February 20, 2019 and Implementation Agreement (IA) have been signed between RNPL and PGCB in 2019.

This project consisting of construction of jetty and coal handling facilities for coal import, coal storage, power plant construction, township development and construction of transmission facilities and road communication. To construct the Power Plant, the company signed EPC Contract with "Consortium of Tianjin Electric Power Construction Co. Ltd., China Huadian Engineering Co. Ltd. and China Wanbao Engineering Corporation (TEPC-CHEC-CWEC) ".

This Power Plant will be run using Ultra-Super Critical Technology along with imported coal. The construction of the Patuakhali Power Plant started on August, 2019. But immediate after the construction began, Covid-19 spread out all over the world. Construction work slowed down for some while, but never been stopped. And now it is very close to make the dream successful.

Power Evacuation Facilities were supposed to be constructed by Power Grid. To secure the implementation of Power Evacuation Related Facilities on an urgent basis RNPL constructed under its management 400 KV AIS switching Station at Amtali, Barguna, 19.30 km double circuit line. Implementation of Power Evacuation Related Facilities is almost done. After LILO connection is established, the substation will be ready for energization and commissioning of the Power Plant will be started.

30 acres of the land is used for resettlement of the people who lost their lands and homes during land acquisition. An attractive residential township has been developed for 281 families along with all the necessary infrastructures like houses, mosque, school, health Centre, market, community center, cyclone center, playground, pond and graveyard. This portion this project is almost ready to handover to the owners.

The 1st Unit (660MW) of the Power Plant is expected to supply electricity commercially to the National Grid by March, 2025 and the whole Power Plant (1320 MW) by June, 2025, subject to getting Back-Feed power received by December 2024.

location_on Location Details

Dhankhali Union, Kalapara Upazila, Patuakhali District, Bangladesh. The site was chosen for its proximity to deep-water maritime access.

schedule Project Lifecycle

A long-term energy commitment with a total project lifespan projected over 25 years of continuous peak operation.

Technical Specifications

bolt
Technology Type

Ultra-Supercritical Coal-Fired

ac_unit
Cooling System

Closed-cycle Cooling Tower

settings_input_component
Steam Parameters

25 MPa / 600°C / 600°C

eco
Emission Control

FGD & ESP Systems Integrated

local_shipping
Fuel Transport

Deep-Water Jetty Access

electric_bolt
Grid Connection

National Power Grid (BPDB)

Financial Structure

Total Assets

BDT 266.4B

266,400,220,818

Total Equity

BDT 67.1B

67,112,804,321

Total Liabilities

BDT 199.3B

199,287,416,497

Revenue

BDT 5.59B

5,592,443,750

Net Profit

BDT 445.2M

445,248,290

EPS

1.04

Earnings per share

Capital Structure
Authorized Capital BDT 70B
Paid-up Capital BDT 52.9B
Share Value BDT 100
Equity Partners
RPCL
15%
Norinco
15%
Exim Bank of China
70%
Debt-Equity Ratio: 70:30

Management

Chairman

Major General S M Zia-Ul-Azim

Managing Director

A.H.M Rashed

Executive Director

Wang Chao

Infrastructure

Marine Jetty

Dedicated deep-water jetty facility designed to accommodate large coal carrier vessels for uninterrupted fuel supply.

Coal Storage

Large-scale covered coal storage facilities ensuring a continuous 30-day fuel supply buffer for uninterrupted operation.

Transmission Line

400 kV high-voltage transmission infrastructure connecting the plant directly to the national grid for bulk power evacuation.

Water Supply

River water intake system for the closed-cycle cooling towers, minimising freshwater consumption with efficient treatment processes.

Project Site

Dhankhali, Kalapara, Patuakhali. Strategically positioned for fuel logistics and distribution.

Open in Maps